WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

315

Discipline/Origin

Drilling
No origin

Well

Canela
6507/7-16 S

Date created

2019/01/07
2526 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Mud
Negative

Island Innovator


What happened in Intermediate section:
Had to increase MW from the planned 1.48 sg to 1.52 sg at TD due to cavings.

What Was Planned

Did not have plan in place for increasing MW upfront, only the planned MW.

What Was Learned

Should use K&M procedures to limit the stress/shocks to the formation.Should get the supplier delivering the geomechanical study to include progressive increase in formation strength.

What Actions Are Required

hould use K&M procedures to limit the stress/shocks to the formation.Should get the supplier delivering the geomechanical study to include progressive increase in formation strength.